Project name
Buxwaha Pawai and Hatta Nagar Parishads in Chhatarpur
-
Project duration
28/12/2016 to 14/062022 -
Status
Completed -
Budget
74.28 Crs
SCOPE OF WORK:
- Construction of RCC U/G Sump and ESRs
- Designing and Construction of RCC framed Pump House.
- Providing, Installation and Commission of Chlorination Plant.
- Providing and Supplying of pump set (centrifugal pump)
- Operation & Maintenance of the WTPs and Water Supply Pipe lines
-
Supply, delivery, lowering, laying, excavation, jointing, testing & commissioning
fitting and refilling of DI Pipes, HDPE Pipe and PVC pipes
SALIENT FEATURES OF THE
PROJECT:
- Water Treatment Plant - 1.30 MLD
- Intake Well -1 No.
- Pipeline - 29,462 Mtr
- House Service Connection
- Pumping Machinery
- LT Feeder - 400 Mtr
For Pawai:
- Water Treatment Plant - 3.70 MLD
- Intake Well -1 No.
- Pipeline - 53,721 Mtr.
- House Service Connection
- Pumping Machinery
- LT Feeder - 2400 Mtr
- OHT - 2 Nos.
81
+
2
+
15.1
MLD +
10
+
81
+
2
+
15.1
MLD +
10
+
Scope of work
- Construction of RCC U/G Sump and ESRs
- Designing and Construction of RCC framed Pump
- Providing, Installation and Commission of Chlorination
- Supply, delivery, lowering, laying, excavation, jointing, testing &commissioning fitting and refilling of DI Pipes, HDPE Pipe and PVC pipes
- Providing and Supplying of pump set (centrifugal pump)
- Construction of Internal road
- Operation & Maintenance of the WTPs and Water Supply Pipe lines